The eighth regular meeting of the 2013-2014 Highview Condominium II, Inc. Board of Directors was called to order at approximately 7:30 p.m.  

Board members in attendance: Robert Boynton, Joseph Cann, Marjorie Cannon, Stacey Cohen, and David Cutler.  Board members absent: Nora Colford, Michael D'Angelo, Natalie Hendrix, and Joseph Skonieczny.  Maria Arzano and Laura Mezzio attended from Wentworth Property Management.  

1)   Minutes:  Minutes of the February 25, 2014 meeting were approved.  

Maintenance update from super:  Chris Brighina reported on building maintenance.  

2)   Building Repair & Maintenance Report:  

a)    Garage masonry repairs: Masonry repairs by KES to two garage access plates completed.  Replacement of one plate remains.  French drain to control water on floor near side entrance on hold as water leak causing condition may have been corrected.  

b)   Installation of backflow restrictor and water filtering:  Filter servicing problem corrected by plumber.  Certifications remain to be scheduled.  Final payment will continue to be withheld until NYC certification received.  

c)    Laundry room:  New dryers now accepting 5-minute payment additions beyond the initial 20-minute charge.  Uncertain whether vendor has added the remote monitoring from smartphones.  A credit of $5 is still to be issued for each unit owner as condition of the renewal contract.  

d)   Hallways, Lobby, Elevator, and Entrance Area Renovation:  Management continues seeking designer recommendations.  Continued discussion.  

e)    Entrance area repairs:  Management has spoken with designer.  Proposal expected.  

f)    Garage wall crack repairs:  Leaks last repaired in July 2002 by epoxy injection.  Abbasi believed to have been the contractor and there was a lifetime warrantee on repairs.  In last 1-2 years have started leaking again.  Super will get estimates.  Management will check records for Abbasi Construction in Brooklyn and conditions of “lifetime warranty”.  

g)   Television Service repair:  Television antenna repair scheduled for this week.  

h)   Spring unit inspections:  Super will schedule spring inspections.  Inspections include plumbing leaks, exterior water infiltration, and battery replacements.  

i)    Compactor room clean-up:  The compactor room has been cleaned up and floor painted.  Arzano will tour with Board after meeting.  

j)    Maintenance log books:  Discussion of maintenance logs (boiler maintenance/service log, boiler water testing service log, and general maintenance log).  Noted that management is responsible for assuring a daily maintenance log.  Highview’s performance guidelines document indicates the written log is to include: “all repairs performed, projects undertaken and/or completed, building problems identified, resident requests, and rules violations.  When projects are completed, completion date should be noted in the log.  When projects involving residents are completed, residents should sign to agree that work has been completed to their satisfaction.”  Management will share 2013 and 2014 logs at next Board meeting.  

k)   Proximity reader keys:  Reviewed that super is to maintain an inventory of 10 proximity reader keys for unit owner and tenant replacements.   

3)   Financial Report  

a)    Unit arrears:  Board reviewed unit arrears with managing agent.  

b)   FY2014 budget:  Budget remains unapproved.  Laura Mezzio reported that she is attempting to confirm where auditor wants the additional $36,500 line item for Capital Reserve savings entered in budget.  

c)    Status of FY2013 Audit:  In progress.  Waiting for FY2013 meeting minutes.  Meeting minutes have been distributed by Board Secretary, but majority of board members have failed to review several of the meetings for approval.  Secretary will re-distribute all FY2013 minutes.  No further update.  

d)   Annual Meeting FY2013:  Will be scheduled as soon as FY2013 audit’s completion date is certain.  

e)    Special Assessment and/or Building Loan:  Comprehensive listing of repair and replacement estimates continue to be gathered.  

f)    Operating and Reserve account balances:  Not reviewed.  

g)   Condominium Tax Abatement:  Process of applying for annual NYC Cooperative and Condominium Tax Abatement was discussed.  In the past, management completed application.  Changes in the law for 2014 require all applicants to indicate units as their primary residence.  Individual Highview owners who completed the NYC forms received their abatements.  Discussion as to whether management can apply on behalf of entire building.  Deadline has past for current year and Arzano will investigate for next year.  

4)   Legal Report:  

a)    Local Law 11 facade inspection (cycle 6) and Local Law 11 facade inspection (cycle 7):  Certification has yet to be completed.  No update in over one year -- 06/26/12.  

b)   NYC code violations:  Continuing discussion of five DOB and five ECB building violations indicated by City as remaining open.  Oldest open violation is dated 11/11/08 and most recent dated 01/15/14.  Management believes that all violations were resolved and building is in full compliance with City codes, however each past violation requires filing with NYC of a Certificate of Correction.  Management recommended that Highview engage a consultant to resolve with City.  Highview has requested that management pay the cost of consultant for resolving the open violations as all of the violations indicated as open are dates attributed to their management term (01/01/08 to present).  As of this Board meeting, consultant has not been engaged.  Noted that this issue was first brought to management’s attention six months ago at the 09/24/13 board meeting.  

c)    Lease compliance:  Arzano will compare records with Boynton.  

d)   Insurance compliance:  All units believed to be in compliance and Arzano reviewing.  Arzano will provide Board Secretary with completed Excel file of current expiration dates for all units.  

e)    Building damage from traffic accident:  Insurance claim in process.  Estimate for repairs received; including masonry work to corner of building, lawn sprinkler system repairs, lawn repairs, electrical repairs, and replacement of bollard lighting.  Update provided and insurance claim still in process.  

The meeting was adjourned at approximately 9:00 p.m  