Highview Condominium II The twenty-first meeting of the 2006-2007 Highview II Board of Directors was
called to order at approximately 7:30 p.m. by Marjorie Cannon, Vice President. Board members in attendance: Miriam Biren, Robert Boynton, Joseph Cann,
Marjorie Cannon, Stacey Cohen, Nora Colford, Michael D’Angelo, Natalie
Hendrix, and Al Lamoglia. Debbie Shapass and Linda Romolo attended from
Wentworth Property Management. 1) Minutes: Minutes of the June 17, 2008 meeting were approved. 2) Financial Report: a) FY2006 audit: Debbie Shapass reported that the FY2006 audit will
be completed next week. b) FY2007 audit: Debbie Shapass reported that the FY2007 has begun.
Wilken & Guttenplan has initially reported insufficient records from TKR. c) FY2008 budget: Waiting for completion of FY2007 audit. d) Unit owners arrears: Delinquent arrears for units 1-B, 4-E, and
3-J have moved to the building’s attorney for collection. All building costs
related to legal costs and collection will be added to the outstanding
balances of these units. Since Unit 6-D had not been billed since their
purchase in March 2007 and TKR management had not accurately kept track of the
outstanding balance for prompt action by the board, the board agreed to offer
the owner a payment schedule of $6,000 (payable within one week of legal
notice) with additional $3,000 and all legal costs payable by August 31, 2008.
If this offer is not accepted within the 1-week period, legal will move for a
complete collection with all interest and legal expenses. Board treasurer
Michael D’Angelo will work with Linda Romolo to assure that this
notification is properly delivered and the building’s attorney acts
accordingly to Highview policy. e) Special Assessment: As approved at the June board meeting,
Wentworth has notified unit owners that Special Assessment for August-December
will begin to appear on August 1, 2008 billings. f) Monthly financial report: Since management’s financial reports
of the previous month have not been available by the regular board meeting now
held on the third Tuesday of the month, the board voted to move regular board
meetings to the fourth Tuesday of the month effective September 2008 at the
recommendation of Debbie Shapass. The previous month’s financial report will
be distributed to officers by email one week prior to the monthly board
meeting. Accordingly the August financial report (closing 08/31/08) will be
distributed by email by 09/16/08 for discussion at the regular board meeting
on 09/23/08. 3) Legal Report: a) Fine Schedule:: Copy of the schedule was not available at the
meeting. Discussion tabled pending distribution. b) Local Law 11: The Local Law 11 inspection report has still not
been filed. Wentworth indicated report is still with former board president
for his signature. c) Leases: Fines of $500 have been issued to several unit owners who
have not responded to management’s reminder to provide copies of their unit
leases to tenants. Additional $500 fines will be issued if compliance is not
achieved within month. d) Unit Arrears: Several delinquent owners have been moved to legal
for collection as noted in the financial report. e) NYC Code violations: Highview currently has two outstanding code
violations. Shapass investigating. f) Emergency contact forms: Linda Romolo reported that she is
working with the board secretary to obtain full compliance of unit owners who
must provide emergency contact forms to management. 4) Building Repair & Maintenance Report: a) Water filtration system: Estimate received from Becht Engineering
in January 2008. Debbie Shapass reported that the other firms she approached
have declined to bid. The board suggested approaching Salamon Engineering who
has previously provided bids to Highview II. It was agreed that Shapass will
contact Salamon and advise board by email of response. If Salamon declines to
bid, the Board will conduct vote on whether to accept Becht bid by email next
week. b) Boiler return pump replacements: There was further discussion of
proposals for boiler return pump and tank replacements. Debbie will get
additional information. c) Garage door repairs: Debbie will meet with Christie Garage Door
about moving the new electric eye to position of the previous one. In
addition, Debbie will have Jose build a cinderblock support to protect the
support arm. d) Fire escape repairs: Welding repairs of fire escapes and rusted
out handrail near garage stairs completed. Exhaust fan system: On 05/13/08, Marco Air investigated ventilation
problems and agreed to inspect A-line and E-line the following week with
management for blockages and/or illegal installation of unit fans. The
inspection has not been completed. The additional ductwork required on the
roof to operate the A-line bathroom fan motor has not been completed by Marco
Air on account of the weather, but is currently scheduled for 07/22/08. f) Elevator repairs: Shapass reported that Slade elevator has made
all repairs from the VSA report. There was discussion as to whether completed
repairs included the list of those required repairs which were not covered by
maintenance contracts or debated with McGlynn Hays (such as the hole in the
roof). Shapass will go back to the initial VSA report and investigate. g) Painting projects: The super is in the process of completing the
garage wall painting, stairwell floors, and unit doors. h) Overhang in front of lobby windows: The roof/overhang in front of
the lobby windows is leaking. Management getting estimates for roof repair.
Only bid to date is $1,200. i) No update on dead Verizon line servicing entrance intercom for unit L-C.
Shapass will discuss with Verizon. j) Garage floor plates: Shapass getting estimates for metal repair
of sewer access floor plates. Shapass indicated that the missing sewer line
cap beneath one of the floor plates will be replaced by Alamonte. k) Smoke detector and CO2 detector battery replacements: Jose has
not completed the spring (semi-annual) replacement of batteries in all units
and common areas. Shapass will provide written report of status at next
meeting. l) Laundry room sink /backflow-restrictor: for drain: Shapass will
have Jose install. The meeting adjourned at 10:05 p.m. Minutes submitted by Robert Boynton, Secretary
Board of Directors - Meeting Minutes
July 15, 2008, 7:30 p.m.