Highview Condominium II
Board of Directors - Meeting Minutes
August 28, 2012  7:30 p.m.

The sixth regular meeting of the 2011-2012 Highview Condominium II, Inc. Board of Directors was called to order at approximately 7:30 p.m. by Stacey Cohen, President.   

Board members in attendance:  Robert Boynton, Stacey Cohen, Marjorie Cannon, Nora Colford, David Cutler, and Natalie Hendrix.  Michael D’Angelo participated during part of the meeting by telephone.  Board members absent:  Joseph Cann and Joseph Skonieczny.  Kristen Teichfuhs attended and was introduced as Wentworth Property Management’s new representative to Highview II replacing Will Boyce.  

1)   Minutes:  Minutes of the June 26, 2012 meeting were distributed by email in July for approval, but have not been approved by the Board.  

2)   Water infiltration:  Engineering report was received by Highview II once payment was received by Becht Engineering.  Contractor bids have been received from Lewis-Graham and K.E.S. Construction.  Bids were reviewed at this meeting.  Kirsten was asked to have them revised for additional detail.  Kristen also asked to get a third bid which is the Board’s policy for major projects such as this.  

Maintenance update from super:  Chris Brighina joined the meeting to report on building maintenance and concerns.  

3)   Building Repair & Maintenance Report:  

      a)   Entrance area repairs:  At May meeting, Boyce requested to get estimates for entrance area crack investigation and threshold repairs.  Carryover from November request to Romolo.  Brighina reported active termite damage to his unit in the area near building entrance.  Noted that in addition to masonry cracks (both vertical wall and floor tile), the exterior cladding is coming loose and possibly water infiltration along with the insect problem.  No update.  Kirsten will report at next Board meeting.  

      b)   Repairs to super’s apartment:  Insect damage will require repairs to wood floors in super’s apartment.  Discussion of the unsupported/hanging cinderblock wall between super’s kitchen and living room requiring addition of header support.  At May meeting, Boyce was asked to investigate.  At June meeting, super volunteered to make header repairs before end of August.  No update at this August meeting.  

      c)   Water supply filtering:  Two bids received.  Kristen Teichfuhs will be familiarizing herself with the situation and get additional bids by next Board meeting.  

      d)   Howard Avenue curb hazard:  Residents cars have been trapped in ditch approximately one foot deep caused by erosion.  In the past, similar situation was resolved by bring to the college’s attention.  Management followed up after last meeting and Wagner College has corrected situation.  

      e)   Landscaping maintenance:  No update on inadequate shrubbery trimming by Prime Landscaping.  Cohen suggested Boynton contact Prime.  Boyce was to get copy of current contract to Boynton for review and then Boynton would meet with Prime.  Management has been unable to locate contract signed by Cohen and is requesting copy of contract directly from Prime.  

      f)    Lobby-level stairwell door damage:  New fire door has been installed and cost passed along to unit 3-A.   

      g)   HVAC system cleaning:  Chutemaster completed cleaning of the building ventilation system in July.  The work included cleaning roof fans, as well as duct work down from the roof and inside all apartment units.  

      h)   Snow Blower:  Brighina noted that snow blower’s lower edge is rusting out.  Skid plate was replaced last year but rust and wear damage was noted at that time to be more significant.  Board agreed to replace snowblower.  Boynton will work with Brighina to select replacement for Board approval.  

4)   Financial Report:  

      a)   Monthly financial reporting: Distributed reports still do not reference FY2012 budget for Board’s remaining FY2012 planning.  

      b)   FY2011 Annual Meeting:  Tentative annual meeting date from February Board meeting was May or June, pending completion of audit.  Then Boyce was to email board with update from Wilken & Guttenplan in June.  Latest report from Cheryl Ruiz indicated early July.  Board has still not received draft of FY2011 audit for review.  No update from Treasurer D’Angelo.  

      c)   Past-due bills:  Discussion of outstanding payments due Alarmingly Affordable, Becht Engineering, Minkel Locksmiths.  Alarmingly Affordable will no longer provide service without payment in advance.  Several plumbing contractors used by Highview in the past have declined to bid on recent projects and indicated poor payment record of Highview as reason.  Board discussed that Operating Account is adequately funded for immediate payment of all expenditures and asked why some bills are going unpaid beyond 90-days.  Questioned whether the unpaid bills from 2011 were included in the FY2011 audit.  Kirsten will investigate.  

      d)   Unit arrears: Legal action recommended against several unit owners.  

      e)   Special Assessment discussion:  With current bids from contractors for exterior repairs at approximately $80,000, the question was called how the building would be paying for this work.  

            Boynton asked whether Capital Replacement Reserve has reached the $250,000 total agree upon and reminded board of vote by unit owners at the October 2009 General Membership meeting to increase Capital Replacement Reserve balance to $250,000 and maintain at that level into future with special assessments as withdrawals are made for Capital Replacements.   

            Boynton noted that the Special Assessment conducted in FY2010 to build the reserve to $250,000 was suspended at $180,000 with the understanding that $37,000 per saving in FY2011 and $37,000 more as a budgeted item in FY2012 would yield the target by end of FY2012 with a closing balance of approximately $254,000 in the Capital Replacement Fund.  Board agreed to review balances at close of FY2012.  

            Noted in discussion that the Operating Reserve, separate from the Capital Replacements Reserve, is calculated as 25% of previous year’s operating (excluding replacement expenditures of those items anticipated by savings as listed in the Capital Replacement Study of 2010).  

5)   Legal Report:  

      a)   Local Law 11 façade inspection (cycle 6) and Local Law 11 façade inspection (cycle 7):  Expediter has submitted Local Law 11 - Cycle 7 to City.  Expediter’s submission was delayed on account of check requested from Wentworth.  No update at this meeting.  

      b)   Update on incident of 04/13/12:  With completion of the lobby-level fire door replacement, fines and cost of repairs have been billed and will appear on the unit owner’s 09/01/12 statement.  

            Summarizing the determination of fines and responsibility for damage.  Evidence included review of video surveillance showing various residents traveling through lobby at time of incident and individual punching fire door and swinging door open with force beyond normal range of travel.  Letters were sent by management to all residents passing through the lobby during the time period requesting that they each provide a written statement of what they witnessed.  Statements were received from residents of six apartment units and all statements indicated that the damage was caused by a single resident, John Mangione of unit 3-A.  The only resident appearing in security video who did not reply to management’s letter requesting explanation of what they witnessed was John Mangione.  Noted by management that Mangione did go to Wentworth’s office to discuss the letter he received, but declined at that time to put anything in writing for Wentworth Management or the Board to consider as mitigating evidence.   

            In addition to cost of replacing damaged door, a $500 vandalism fine was issued and a $500 noise disruption fine.  It was noted that the Building Rules specifically state that a $500 Vandalism fine is in addition to cost of all repairs resulting from the vandalism.  And although an initial noise disruption fine is $100, the violator had previously been warned in writing and fined for this type of offense and the Building Rules state that a second or later violation is $500.  

      c)   Parking garage:  Complaint presented to Board on 05/24/12 that exit door is being illegally blocked by owner of space # 5.  Board reviewed that doorway (egress) is 35” wide and New York State code may require an access aisle of equal or greater 35”.  Noted that each parking space is a different dimension and larger cars and trucks do not fit in some spaces.  Will Boyce was to confirm New York State building code as it relates to aisle with for egress.  No update.  Kirsten Teichfuhs will review and report back at next meeting.  

      d)   Water damage to apartment unit from sprinkler system:  A pipe from the lawn sprinkler system broke, resulting in water sprayed into lobby level unit L-H through a living room window.  Carpeting was soaked and removed to dry out by super, however wood flooring has warped and is raised as much as 6” in the living room and dining area.  Repair will require extensive removal of all living room and dining room flooring.  Estimates for repairs reviewed by Board.  Estimates did not include costs of moving and storing furniture and hotel expenses.  Board questioned building insurance issues, insurance deductible, and whether to seek insurance claim or make repairs out-of-pocket according to building’s responsibility per Bylaws.  Kirsten will review situation and building’s insurance.  

      e)   Leases:  All unit owners with rentals are required to provide management with a copy of their current lease and related information required.  There is a $500 fee for new rentals and $300 fee for annual renewals.  At June meeting, Boyce was checking whether all rental units were up-to-date and complete, whether both FY2011 and FY2012 fees were billed and collected, and Boyce would then provide documentation to Board secretary for files.  No updates were received from Boyce and Secretary (Boynton) is now working directly with Maureen Gentile at Wentworth to verify the situation.  

      f)    Insurance:  All unit owners are required to provide management with a copy of their current apartment insurance (declaration sheet only).  At the June meeting, Boyce was checking whether all units were in compliance and would be providing documentation to Board secretary for files.  No update at this meeting.  

The meeting was adjourned at approximately 9:30 p.m.  

Minutes submitted by Robert Boynton, Secretary.