Highview Condominium II
Board of Directors - Meeting Minutes
September 23, 2008, 7:30 p.m.
The
twenty-third meeting of the 2006-2007 Highview II Board of Directors was called
to order at approximately 7:30 p.m. by Marjorie Cannon, President.
Board
members in attendance:
Miriam
Biren, Robert Boynton, Marjorie Cannon, Anna Civitano, Stacey Cohen, Nora
Colford, Natalie
Hendrix, and Michael D’Angelo.
Linda Romolo attended from Wentworth Property Management.
Board member Joseph Cann was absent.
1)
Minutes: Minutes of
the August 19, 2008 meeting were approved.
2)
Appointment of new board member:
Per the board’s appointment decision made at a meeting on September 22,
2008, Anna Civitano was welcomed to the board, filling the vacancy created by
Albert Lamoglia’s 09/04/08 resignation.
3)
Financial Report:
a) FY2007 audit:
Treasurer Michael D’Angelo updated the board on Wilken &
Guttenplan’s progress with the FY2007 audit.
Audit completion is anticipated in early November.
Difficulties in confirming FY2007 records from TKR Management continue.
b) FY2008 budget:
Waiting for completion of FY2007 audit.
c) Unit owners
arrears were discussed. Due to
multiple months of arrears, legal action is being taken on the following units:
1B, 2J, 3J, 4E, and 6D.
d) Monthly financial
report: Once again it was
reviewed that the monthly financial report will be distributed by email to all
board members one week prior to the monthly board meeting.
The distribution by CD costs too much.
4)
Legal Report:
a) Highview’s Rules & Regulations and Fine Schedule were reviewed. The fines for the following violations were raised:
·
Vandalism/Destruction of
property – raised from $100 (plus cost of repairs) to $500 (plus cost of
repairs).
·
Unauthorized/improper use
of roof area – raised from $100 to $250
·
Parking in circular
driveway – raised from $25 to $100 (plus towing costs)
·
Failure to follow pet
walking rules – raised from $25 to $100
·
Obstruction of common
areas– raised from $25 to $100
·
Washing cars on common
property– raised from $25 to $100
·
Excessive noise– raised
from $50 to $100
·
All remaining $25
violations – raised from $25 (per occurrence or per month until corrected) to
$50 (per occurrence or per month until corrected)
·
Improper disposal of
household garbage or recycling – raised from $50 first offense and $100 for
second offense to $100 (no later a distinction between first or later
offense).
The above listed changes in fines to be effective as of this evening’s
meeting.
b)
The Repair and Renovation rule (House Rule #22) will be re-written to
specifically exclude plumbing and electrical work from being performed outside
the super’s regular business hours unless written permission has been obtained
through the Managing Agent. In cases
of emergency, management must still be contacted at the time of the emergency in
order for the building super to evaluate the situation’s impact on surrounding
units.
22.
Management must be notified in advance and approve in writing of all
plumbing and electrical repairs and renovations, or in case of any other repair
or renovation project within a unit such as bath tub or floor refinishing that
may transmit hazardous fumes or particulate matter beyond the unit under
renovation. The written approval
received from management must specify the days and times of approved work before
the work commences.
In order to verify that projects
are carried out in accordance with building rules and in order to assure that
the building super is available in case of potential emergency situations,
management may determine that a given project may not be conducted beyond the
super's regular work hours.
In cases of emergency, the super or management must
be notified before repair work commences in order to avoid a fine.
NYC Building and Fire code rules must be followed.
c) NYC Code
violations: Highview currently
has one outstanding code violation for the elevator.
Linda Romolo investigating with Slade Elevator.
No update at this September meeting.
d) Emergency contact
forms: Per August board meeting
Linda Romolo reported that all but four units have complied with submission of
Emergency Contact Form. Remaining
four units will be reminded once more and then fined.
No update at this September meeting and delinquent unit owners have not
been fined.
5)
Building Repair & Maintenance Report:
a) Water
filtration system: At the August
meeting, the engineering decision was tabled pending Linda Romolo’s request
that the board delay the decision for her to make an inquiry for technical
guidance. It was agreed that the
board would vote by email once Linda’s inquiry was completed.
There has been no update since the previous meeting.
Further discussion of a water filtration system was tabled.
b) Boiler return pump
replacements: There was further
discussion of proposals for boiler return pump and
tank replacements at the August meeting and Linda was to provide additional
information at this September meeting. There
was no update at this September meeting. Concern
was expressed for the need to provide building heat in October.
c) Exhaust
fan system:
On 05/13/08, Marco Air investigated ventilation problems and agreed to
inspect A-line and E-line the following week with management for blockages
and/or illegal installation of unit fans. The
inspection has not been completed. The
additional ductwork required on the roof to operate the A-line bathroom fan
motor has not been completed by Marco Air on account of the weather, but is
currently scheduled for 07/22/08. As
of this September board meeting, the unit inspections have not been scheduled
and the ductwork repairs have not been verified, and the A-line bathroom fans
continue to operate at high speed.
d) Elevator repairs:
Shapass reported that Slade elevator has made all repairs from the VSA
report. There was discussion as to
whether completed repairs included the list of those required repairs which were
not covered by maintenance contracts or debated with McGlynn Hays (such as the
hole in the roof). Shapass will go
back to the initial VSA report and investigate.
There was no update at this September meeting.
e) Painting
projects: The super has
completed painting of the garage walls and stairwell floors.
Unit doors project remains and will require opening of each unit door.
There was no update at this September meeting.
Concern was expressed for completing the task prior to the heating season
and the need to provide adequate building ventilation during the painting
process.
f) Overhang in
front of lobby windows: The
roof/overhang in front of the lobby windows is leaking.
Management getting estimates for roof repair.
Only bid to date is $1,200. No
update since the July meeting. Problem
appears to be worsening.
g) Intercom repair:
The board approved a new circuit board to replace a 1988 part.
h) Garage floor
plates: Linda
Romolo investigating metal repair of sewer access floor plates.
Linda Romolo will also review status of
missing sewer line cap beneath one of the floor plates that required replacement
cap. Super should be able to
purchase cap. No update on either
issue at this September meeting.
i) Smoke
detector and CO2 detector battery replacements:
Jose has not completed the spring (semi-annual) replacement of batteries
in all units and common areas. Written
report of status was to be provided at the August meeting from super.
Linda Romolo will investigate status.
There was no update at this September meeting.
It was agreed that the spring replacement had failed and the October
replacements should now be completed with proper verification before the next
board meeting.
j) Laundry room
sink /backflow-restrictor: for drain: Shapass
indicated super would install. Linda
Romolo will investigate status. No
update at this September meeting.
The
meeting adjourned at approximately 9:30 p.m.
Minutes
submitted by Robert Boynton, Secretary