The first meeting of the
2009-2010 Highview Condominium II, Inc. Board of Directors was called to order
at approximately 7:40 p.m. by Stacey Cohen, President.
Board members in
attendance: Robert Boynton, Joseph
Cann, Marjorie Cannon, Stacey Cohen, Nora Colford, Natalie Hendrix, Angelo
Morelli, and Joseph Skonieczny. Board
member Michael D’Angelo was absent, but was called for discussion of
particular issues.
Linda Romolo attended from Wentworth Property Management.
1)
Minutes: Minutes of
the September 29, 2009 meeting were approved.
2)
Maintenance update from super:
Chris Brighina joined the meeting for a short period of time to report on
building maintenance items and concerns.
3)
Financial Report:
a) Unit Owner Arrears.
Status of legal actions were discussed.
b) Operating and
Capital Reserve Account balances were discussed.
c) Audit for FY2008:
The final version of the FY2008 audit will be completed shortly, but was
not available at the FY2008 General Membership Meeting on October 28, 2009.
The independent auditor from Wilken & Guttenplan was present at the
General Membership Meeting and indicated that only be a couple minor corrections
to the final document remained, but that the building’s general financial
health was satisfactory.
d) Capital Reserve
discussion: There was discussion
of the need to increase Capital Reserve and the opinions expressed by unit
owners at the FY2008 General Membership Meeting:
At the General Membership Meeting on October 28th, unit owners
were polled for their opinion on increasing the Capital Reserve fund.
The auditor attending the meeting from Wilken & Guttenplan
recommended to the general membership that the Board consider updating the
Capital Reserve Study of 2003, since the 15-year forecast is now 7 years old and
does not take into account replacements beyond 8 years.
In the past 7 years, the building has completed approximately $150,000 of
the ~$750,000 in capital replacements anticipated in the 2003 report –
leaving approximately $600,000 in potential replacements in the next 8
remaining years. At the same time,
an updated report would reach a full 15 years into the future for expenses that
the board should prepare for.
The 2003 Study had recommended an immediate assessment over six months of
$100,000 and continued additions to the reserve fund of approximately $37,000
each year. However with dramatic
increases in building expenses for energy (heat, electricity), insurance, and
taxes, delayed implementation of the Study’s recommendations for Capital
Replacement savings.
In discussion of 1) how the cost of either a boiler or elevator
replacement would exceed $100,000, 2) both systems have exceeded their typical
life span, and 3) a failure either boiler (heat/hot water) or elevator might
force a system shut down until the required funds could be raised from all of
the 67 unit owners, there was general agreement that the increase in reserve is
urgently needed. It was also noted
that while the building had arranged for a building loan when the roof was
replaced several years ago, getting an emergency loan for future replacements
might be unlikely in today’s financial climate and with the condominium
corporation not having any real property to offer as collateral.
Without dissenting opinion when the General Membership was polled at the
annual meeting and with a quorum of unit owners represented, membership’s
opinion was that 1) Capital Reserves should be increased by $200,000-$300,000
and 2) a significant special assessment should be conducted for this purpose
(instead of a small common charge increase that could cover the same amount but
take a much longer period of time to accumulate the amount discussed).
As the final decision in the matter rests with the Board, there was
lengthy discussion in the matter at this November meeting.
D’Angelo recommended a three-year assessment for the full amount.
Cohen suggested waiting until summer be begin the assessment.
Skonieczny requested an option for unit owners to be able to pay their
entire share at the outset of the Assessment.
Boynton recommended incremental/annual renewals of the Assessment to
provide some flexibility in the decision and annual review by the board of
capital needs. The board decided to
hold a special board meeting on December 8, 2009 for the purpose of determining
the amount and term of a special assessment to increase the Capital Reserve.
The matter was tabled until December 8th.
4)
Legal Report:
a) Rules &
Regulation fines: A $500 moving
fine was issued to a unit owner for the action of their tenant.
A $100 parking fine will be issued to a unit owner for parking in the
driveway for 3 hours over the weekend.
b) Damage to common
property: In review of
management’s decision, a unit owner was determined to be liable for the
building’s cost of replacing a unit door and frame as common property
of the building. The same unit owner
was found to be liable for the cost of repairing damage to the front entrance
door and security system. Romolo was
asked to complete the replacement without further delay and bill the owner.
There was concern that the damaged door needs to be replaced before the
Thanksgiving/Christmas/Chanukah holiday season when the guests of unit owners
will be visiting.
c) Unit owner
liability insurance: The Board
approved changes in the Rules & Regulations and a new rule was approved that
will require unit owners to carry liability insurance covering potential damage
to surrounding units and common property. The
final wording of this regulation will be reviewed by the building’s attorney
prior to final approval by the board.
d) Board member
elections at the FY2008 General Membership Meeting:
The FY2008 General Membership Meeting took place on Wednesday, October
28, 2009. Joseph
Cann, Angelo Morelli., and Joseph Skonieczny were elected to three year
terms.
e) Local Law 11 façade inspection (cycle 6):
There was no update. At the
September meeting, Romolo indicated that the building would be re-submitting the
Cycle-6 engineering report for Local Law 11.
City will then inspect and provide certification along with any needed
repairs.
f) Unit Leases:
Romolo indicated that all unit owners are currently in compliance with
Highview’s lease approval and renewal requirements.
g) Update on NYC
rebuilding of Clove Road:
Super is including search for building cracks in structural walls in his
unit inspections. Once completed,
Becht Engineering will follow up.
6)
Building Repair & Maintenance Report:
a) Exhaust
fan system: Super is
currently verifying adequate operation in lobby and first floor units,
inspecting all units for illegal within-unit fan installations or construction
which may have blocked building access to common property vents, and that the
building’s ventilation system is operational as required by NYC code.
With completion of his inspections, a ventilation contractor will inspect
any non-functioning lines by camera by the end of the year.
b) Painting projects:
Brighina has completed painting of most
unit doors and common area doors.
c) Semi-annual smoke
detector replacements and unit inspections:
Brighina reported that he has completed about a
third of the fall unit inspections and is to complete remainder of building
before Thanksgiving. Board reminded
residents at the annual General Membership Meeting on October 27th
that super will require access to all units.
d) Replacement/upgrade
of exterior and lobby lighting timers: The
two bids were not for identical work. Joe
Cann will review bids with Chris and authorize most appropriate work without
further board input.
e) Parking lot crack
repairs: Chris has been
repairing the parking lot cracks. It
was again noted that since the parking lot walls were painted last year and the
wall lines painted over, the wall lines urgently need to be restored prior to
winter, when even a dusting of snow will make the pavement lines invisible to
the owners of the spaces and difficult for them to stay within their very
limited space allocations.
From the September board meeting, Linda Romolo was to get bids for
parking lot sealing and resurfacing for the board’s information and future
consideration. Romolo had no bids at
this meeting.
f) Boiler
circulation pump #2 replacement: Completed.
g) Landscaping:
The board approved a new landscaping contractor (Prime) for 2010 season.
h) Plumbing
investigation of possible break in drain pipe:
Plumber suggested that current leak may be in sprinkler system pipes
instead of building drain pipes. Now
that sprinkler system has been drained for the winter, super will monitor for
further signs of leakage into parking garage.
If flooding occurs, board authorized super to call plumber in to camera
the line. Prior break was identified
in the drainage line and a temporary patch was installed at that time.
i) Garage door
operation: There was discussion
at the September meeting of the garage door’s emergency systems.
It was determined that the overhead door does not stop and reverse when
it is closing and encounters an object in its path, there is no emergency
release for the door, and super noted that a load bearing cable had started
fraying. No update from Romolo at
this meeting.
j) Underground
fuel oil tank.: No update from
Romolo. Operating license from NYC
expires in November
k) Entrance area tile
cracks: There was discussion of
cracks in exterior entrance area tile and loose grout at the September meeting
and management was to investigate and provide repairs bids so that repairs can
be completed before winter. There
was no update from Romolo at this meeting.
l) Carpet
cleaning: Carpet cleaning was
completed last week.
m) Lobby ceiling:
The building super will replace the ceiling access panels and touch-up
the ceiling as needed before the holidays.
n) Plumbing repair:
The sprinkler head in the laundry room is still dripping.
o) Flower bulb
planting: Nora Colford will
oversee planting of additional bulbs. $200
was authorized.
p) Entrance area:
There was discussion of the tile cracks and grouting problems in the
exterior front entrance area. Romolo
will get bids for repairs to be made before cold weather leads to additional
damage.
q) Damaged compactor
chute door on third floor: Romolo
reported that the 3rd floor compactor chute door will be replaced by
NuWay.
r) Telephone
pole damage: Romolo was asked to
follow-up with the City concerning the damaged telephone pole as a risk to
building property and residents.
s) Carpeting
replacement: Romolo and Cohen
investigating.
t) Fire Escape
repairs: Romolo tending to fire
escape inspection and getting multiple bids for and repairs outside unit 3-E.
u) Elevator repairs:
Romolo to arrange 3rd party inspection of elevator.
Other
business:
a) December Holiday
Party: The date of December 15th
was set for the annual holiday party. Marjorie
Cannon was authorized $500 for food and beverages.
b) Building staff:
Super due for evaluation. Meeting
will be scheduled with Cohen and Romolo.
The meeting adjourned at
approximately 9:45 p.m.
Minutes submitted by Robert Boynton, Secretary