Highview Condominium II
Board of Directors - Meeting Minutes
December 27, 2015 7:30 p.m.
The third regular meeting of the 2015-2016 Highview Condominium II Board of
Directors was called to order at approximately 7:30 p.m. by Robert Boynton,
Secretary.
Board members in attendance: Robert Boynton, Joseph Cann, Marjorie Cannon, Joan
Desantis, and Madalina Rauscher.
Joining the meeting later: Sindhu Mathew and Natalie Hendrix Lombardo.
Board members absent: Michael
D'Angelo and Rosanna Fernandez.
Siobhan Hickey and Marissa Zinnanti attended from Carriage House Property
Management.
1) Approval of 09/28/15
Minutes: Minutes were approved
by email.
2) Building Repair &
Maintenance:
a)
Fire escape - welding and painting bids:
Bid by Maximum Welding for both repairs and painting was approved by
email on 10/06/15. Contractor has
started work and anticipates three weeks to complete.
b)
Foundation crack repairs:
Repairs completed by Tan Interiors.
Engineering inspection by Salamon Engineering completed.
c)
Parking lot resurfacing:
Bid tentatively approved at August meeting while questions remain
concerning milling process. Seeking
feedback from Salamon Engineering as four contractor bids not necessarily
identical. No update.
d)
Front entrance area sidewalk renovation and pillar crack repair:
Bid by Milano approved.
e)
Front entrance refinish of doors/windows bids:
Bid received for refinishing doors to original condition.
Boynton requested discussion with contractor concerning explanation of
process.
f)
Wallpaper and carpet replacement:
Although contract signed for work, project on hold pending completion of
building loan. Anticipate January start date.
g)
Compactor room - toilet installation:
Awaiting completion of design work by Salamon Engineering.
h)
Electrical back-up - generator system:
Awaiting completion of design work by Salamon Engineering.
i)
North-end sidewalk &stairwell repairs:
Management continues to receive contractor bids.
j)
Garage - French drain at garage stairwell doorway:
Awaiting bids.
k)
Garage floor - concrete failure near entrance:
Awaiting bids.
l)
Water infiltration reports:
Fall 2015 unit inspections began at end of September and approximately
50% of units still to be inspected.
Once complete, exterior masonry repairs can be bid.
m)
Security upgrades/repairs:
Portions of the project scheduled for November completion.
n)
Television antenna servicing:
Building's antenna scheduled for repair service by Quality Antenna week
of 11/23/15.
o)
Maintenance Committee:
Committee indicated that they have not been making weekly inspections.
Members did not have the inspection report form.
Copy will be distributed tomorrow to Sindhu.
p)
Boiler servicing and repairs:
Plumbing repairs by PAC to be completed this Friday, 10/30/15.
Per Joe Cann's recommendation, Starr Boiler will continue to service
burner /combustion issues. Salamon
Engineering's report indicated circulation water system could possibly use
flushing. No update on flushing.
q)
Landscaping Committee:
Discussed fall flower bulb planting, entrance area bench, exterior
lighting, condition of sidewalks, and other exterior landscaping issues.
Cannon chair. Members
include Cannon, Mathew, Boynton, Desantis, and Fernandez.
r)
Office computer:
Madalina Rauscher will be picking up computer cable for the Time Clock
connection to computer.
s)
Elevator breakdown and emergency response by Slade:
Noted that Alarmingly Affordable offers emergency telephone support.
Boynton will speak with them tomorrow for details.
4) Financial Report:
a) Unit arrears:
Board reviewed unit arrears with managing agent.
b) Building Loan:
Comprehensive listing of repair and replacement estimates continue to be
gathered. Board Treasurer
maintaining a current list. Loan
discussions with banks continuing.
c) Audit for FY2015:
FY20015 audit contract to be signed with Wilken & Guttenplan in
October/November.
d) Monthly financial
reporting: Board has requested
monthly financial report to reflect budgeted versus actual by cost center as
well as YTD figures. Should
indicate budget remaining in various cost centers.
5) Legal Report:
a) Unit liens:
Management will discuss status of units with building's attorney.
b) Local Law 11 facade
inspection (cycle 7): Working
with Salamon Engineering on fire escape repairs and follow up to 01/2015.
c) NYC code
violations: One DOB building
violation indicated by City on their website as remaining open/active.
Management indicates violation is from 2012 and will require an
engineering report. At 09/2015
meeting, Board approved Salamon Engineering to conduct the 2012 report required
by NYC. No update.
d) Lease compliance:
Presently one unit in violation and receiving $500/mo. fine.
e) Insurance
compliance (owner coverage):
Reviewed.
f) Insurance
compliance (leased units/tenant coverage):
Reviewed.
g) Insurance claim:
Possible claim against the building discussed.
Not certain whether claim is against 830 Howard Ave. or 850 Howard Ave.
No update.
h) Contact information for
unit 3-D and 4-G: Discussed
status of unit and legal contact information.
6) Summary review of
meeting's action items: Not
reviewed.
The meeting was adjourned at approximately 9:20 p.m
-